President Trump Takes Action to Expedite Priority Enery and Infrastructure Projects

Staff Report

Wednesday, January 25th, 2017

President Donald J. Trump signed a series of Executive Orders and Presidential Memoranda in keeping with his promise to reduce the burden of regulations and expedite high priority energy and infrastructure projects that will create jobs and increase national security.

Presidential Memorandum Regarding Construction of the Keystone XL Pipeline

With this Presidential Memorandum, President Trump will help fulfill the campaign promise of initiating the process for approving the Keystone XL Pipeline.

The Keystone XL Pipeline is an 1,100-mile crude oil pipeline to connect oil production in Alberta, Canada to refineries in the United States.

Construction and operation of the Keystone XL Pipeline, as well as oil production and refining activities related to it, would create tens of thousands of jobs for American workers, enhance our nation’s energy security, support affordable and reliable energy for American families, and generate significant State and local tax revenues that can be invested in schools, hospitals, and infrastructure.

Presidential Memorandum Regarding Construction of the Dakota Access Pipeline

With this Presidential Memorandum, President Trump directed the relevant Federal agencies (including the Army Corps of Engineers) to expedite reviews and approvals for the remaining portions of the Dakota Access Pipeline., a $3.8 billion, 1,100-mile pipeline designed to carry around 500,000 barrels per day of crude oil from the Bakken and Three Forks oil production areas in North Dakota to oil markets in the U.S.  

At this time, DAPL is more than 90% complete across its entire route.  Only a limited stretch of the project is not yet constructed. Timely review and approval of energy pipelines is critical to a strong economy, energy independence, and national security.

Presidential Memorandum Regarding Construction of American Pipelines

In keeping with his commitment to “Buy American, Hire American”, President Trump directed the Secretary of Commerce, in consultation with all relevant executive departments and agencies, to develop a plan under which all new pipelines, as well as retrofitted, repaired, or expanded pipelines, inside the borders of the United States, including portions of pipelines, use materials and equipment produced in the United States, to the maximum extent possible and to the extent permitted by law.  The Secretary shall submit the plan to the President within 180 days of the date of this memorandum.

Presidential Memorandum Streamlining Permitting and Reducing Regulatory Burdens for Domestic Manufacturing

With this Presidential Memorandum, President Trump helps fulfill the campaign promise of boosting domestic manufacturing by determining a plan of action for expediting approvals for manufacturing and reducing regulatory burdens.

Under this Presidential Memorandum, the Secretary of Commerce will conduct outreach to stakeholders and solicit comments from the public concerning Federal actions to streamline permitting and reduce regulatory burdens affecting domestic manufacturers. 

The Commerce Secretary will submit a report to the President identifying recommendations to streamline Federal permitting processes for domestic manufacturing and to reduce regulatory burdens affecting domestic manufacturers. The report should identify priority actions as well as recommended deadlines for completing actions.  

Executive Order Expediting Environmental Reviews and Approvals For High Priority Infrastructure Projects

With this Executive Order, President Trump will establish a framework for expediting environmental reviews for high priority infrastructure projects. 

Delays and other inefficiencies in the environmental review and permitting process are severely impeding critically important projects to rebuild and modernize our nation’s infrastructure, such as highways, bridges, tunnels, the electrical grid, ports, water systems, airports, railways and pipelines.

According to one study, our antiquated power rigs wastes the equivalent of 200 coal-fired power plants, water pipes leak trillions of gallons of water, and gridlock on roads and railroads wastes hundreds of billions annually.